Verrano InstrumentsSummit decision room with Sablewood Events
More
Theme
Ask Simone
Nathaniel ObuyaHead of marketing events, Verrano
Decision path 2 of 10Keynote format Oct 7

Options

Each open decision with the answers Verrano can give, what each costs and what it releases. Sablewood recommends; Nathaniel decides.

Format due Oct 7Changes due Oct 8Acceptance Oct 9

Decision 1, recommended answer

Choose the keynote format by Oct 7

Brindlemoor Staging can then reconfirm the expired quote and fix the stage dimensions.

  • Staging quote reconfirmed by Simone Vrabec
  • Oct 9 staging deposit approved at the quoted price
  • Stage fixed for the build
  • Keynote stage layout decided on Oct 8 with the format known

$3,200

Reprice risk avoided on the main stage

Decision by
Oct 7
Quote expired
Sep 25
Deposit due
Oct 9
Send your choice

Send it through the project space so it reaches the change record.

See the supplier items

The other answer

  • Choose after Oct 7Brindlemoor cannot hold its price. The Oct 9 staging deposit cannot be approved at the quoted price and the stage cannot be fixed for the build.
    Stage price
    Up to $3,200 more
    Deposit Oct 9
    Held

    Up to $3,200 more

Simone Vrabec asks Brindlemoor to reconfirm as soon as the format is chosen, whenever that is.

Decision 2: the two open changes

Change log

Kofi Adjei prices both on Oct 5, before any supplier call. Nathaniel Obuya decides both by Oct 8.

Open changeAnswerPriceWhat it releases
Keynote stage layoutAcceptPriced by Kofi Adjei on Oct 5Stage work booked with the staging supplier once the format is known
Keynote stage layoutDeclineNo chargeNo supplier work booked, as with the two earlier declined changes
Customer panel sessionAcceptPriced by Kofi Adjei on Oct 5Larchmere Conference Center holds the room and version 8 carries the session
Customer panel sessionDecline, or decide after Oct 8No chargeThe session stays out of the released agenda

For scale

The four priced changes Verrano accepted come to $21,300.

  • Keynote stage lightingPennywhistle Audio Visual, confirmed$8,200
  • Day 2 closing extensionPennywhistle Audio Visual, confirmed$5,400
  • Plated lunch upgradeFairweather Catering, confirmed$4,700
  • Speaker highlight reelQuillhaven Film Studio, in production$3,000

Decision 3: accept the Sep 10 sales kickoff

Acceptance record

Answer A

Accept once the video and photo library arrive

Simone Vrabec delivers both by Oct 7 and Nathaniel Obuya records acceptance by Oct 9.

  • The $86,400 final invoice is released by the Sablewood controller
  • The $450 badge credit shows as its own line, so the invoice amount is not edited
  • The badge deliverable is recorded as accepted with the credit noted

Answer B

Hold acceptance

Verrano can hold acceptance if either deliverable is late or not as agreed.

  • The final invoice stays unreleased and keeps waiting since Sep 10
  • The 60 misprinted badges still count as not accepted
  • The 10 business day window ended Sep 24, so Oct 9 is an agreed exception, not the standard date

Deposit schedule, $46,500 in five payments

Supplier status

Nothing to choose here. Kofi Adjei approved the schedule and the Sablewood controller releases each payment on its date.

DueSupplierWaits onVerrano input
Oct 9Brindlemoor StagingQuote reconfirmedKeynote format, by Oct 7
Oct 12Pennywhistle Audio VisualNew breakout screens quoteNone
Oct 12Fairweather CateringFinal headcountDay 1 lunch headcount, by Oct 9
Oct 14Quillpoint BadgingLate arrival countExpected late arrivals, by Oct 9
Oct 15Quillhaven Film StudioSpeaker permissionsWritten permission from each speaker, by Oct 12

Staging quote and keynote format

What the stage price waits on.

Live from the Dashboards appOpen the full report

Supplier items by deliverable and state

All 23 items on Sep 21.

Live from the Dashboards appOpen the full report