Decision path 2 of 10Keynote format Oct 7

Changes

Every change with its price and decision. Two wait on Verrano: Kofi Adjei prices them by Oct 5 and Nathaniel decides by Oct 8.

Change decision log, updated Sep 28, 2026
An event producer and a client reviewing a change request on a venue floor during build

Changes at a glance

Status as of Sep 28, 2026 2 changes waiting on a decision 1 change started before a decision

Every change Verrano Instruments has requested for the Verrano Summit 2026 on November 12 and 13, with its price and its decision, so that no work starts before the decision is recorded. Prepared by the Sablewood producer for Nathaniel Obuya, Head of marketing events at Verrano Instruments, and for Verrano procurement. Fourteen changes are logged: 6 included at no cost, 4 priced and accepted for $21,300 in total, 2 declined and 2 waiting on a decision.

Changes logged14since kickoff
Waiting on a decision2both decided by Oct 8
Priced and accepted$21.3K4 changes
Absorbed by Sablewood$1.9Kstage extension

Changes by area of the event

Read the table by row. Each row is an area of the summit and each column is a decision state, so the numbers across a row add up to the total for that area. Agenda and sessions has the most changes (4). Stage and set and Agenda and sessions each hold one change that is still waiting on a decision.

Live from the Dashboards appOpen the full report

What is waiting on Verrano

Two changes have no decision yet. Both will be priced before any supplier call, and both are decided by Oct 8.

ChangeStatus in the logNeedsDate
Keynote stage layoutClient review UrgentKeynote format decision from Nathaniel Obuya; the staging quote expired on Sep 25 with a $3,200 reprice riskFormat by Oct 7, decision by Oct 8
Customer panel sessionClient review HighPrice set by Sablewood; the room depends on the breakout room changeDecision by Oct 8
Live from the Dashboards appOpen the full report

From requested to accepted

The chart starts at the 14 changes requested. It takes off the 2 declined and the 2 waiting, which leaves 10 that are included or priced and accepted. Those 10 split into 6 included at no cost and 4 priced and accepted.

The four outcomes, with the exact changes in each:

Included at no cost (6)

ChangeAreaStatus
Stage extensionStage and setIn production
Day 1 afternoon sessionAgenda and sessionsPlanning
Breakout moderator swapAgenda and sessionsComplete
Late registration deskRegistration and badgingPlanning
Gluten free stationCatering and hospitalityConfirmed
Keynote speaker hotel nightSpeaker travelPlanning

The stage extension is on this list because Sablewood absorbed its cost, as the callout below explains.

Priced and accepted (4)

ChangeSupplierPriceStatus
Keynote stage lightingPennywhistle Audio Visual$8,200Confirmed
Day 2 closing extensionPennywhistle Audio Visual$5,400Confirmed
Plated lunch upgradeFairweather Catering$4,700Confirmed
Speaker highlight reelQuillhaven Film Studio$3,000In production

The four prices add up to $21,300.

Declined (2)

ChangeSupplierWhat happened
Late night receptionFairweather CateringDeclined; no supplier work booked
Same day video editQuillhaven Film StudioDeclined; no supplier work booked

Both rows show Complete in the log because the decision is closed.

Waiting on a decision (2)

Keynote stage layout and Customer panel session. Both are in Client review and both need a decision from Nathaniel Obuya by Oct 8.

Live from the Dashboards appOpen the full report

No work before a decision

The change rule

Change rule
No production work before a recorded inclusion or price decision.
Where requests go
Through the project space only. Nathaniel Obuya agreed to send every request there, so a text message or a hallway request is not yet a request.
Who checks feasibility
Simone Vrabec, Executive producer, with the supplier named in the log.
Who decides the commercial outcome
Kofi Adjei, Managing director: included, priced, absorbed or declined. Both open changes are priced before any supplier call.
Who approves
Nathaniel Obuya approves the change inclusion and price. The approved version returns to the log and only then does supplier work start.
What the log counts
Each change shows requested, priced, decided and accepted, plus any cost absorbed and any work started before a decision.

Approval steps for a client change

  1. Request logged in the project space
  2. Feasibility checked by the producer
  3. Inclusion and price set by Kofi Adjei for 12 changes
  4. Price the two open changes, Oct 5
  5. Verrano decision on the two open changes, Oct 8
  6. Supplier work booked
  7. Accepted version recorded in the log

Before Oct 8

  • Agree that requests go through the project space only. Owner: Nathaniel Obuya, donedone
  • Price the Keynote stage layout and the Customer panel session before any supplier call. Owner: Kofi Adjei, Oct 5open
  • Choose the keynote format so Brindlemoor Staging can reprice. Owner: Nathaniel Obuya, Oct 7open
  • Decide both open changes. Owner: Nathaniel Obuya, Oct 8open
  • Record both decisions in the log and book supplier work. Owner: Simone Vrabec, Oct 9open

"A change is real when it has a price and a decision in the log. Until then it is a question, and no supplier gets a call."

Kofi Adjei, Managing director, Sablewood Events

Who is on this log

  • Nathaniel ObuyaHead of marketing events, Verrano Instruments, approves each change

  • Kofi AdjeiManaging director, Sablewood Events, decides included, priced, absorbed or declined

  • Simone VrabecExecutive producer, Sablewood Events, checks feasibility and books supplier work